Deployment

         

First contact of the German and Yugoslav official’s about delivery of combat planes held in Alterheim in Switzerland, in September 1935. Two months later, Yugoslav commission had tested one of the first prototype of Do17, powered with BMW engines. Yugoslav officials held a negotiation with Dornier of the delivery of Do17 and Do22 in total amount of 2.000.000 RM but Herman Goring had influence as his opinion was that solutions was too good for Yugoslavs. But information that Yugoslav could got credit for military planes from France disturbed German side and after continued negotiation contract was sighed at November 1936. for delivery of twenty Do17. By the proposal, first plane should be ready and delivered at May 9. 1937.

 

          Yugoslav sent a commission whose task was to accept new produced planes. Regarding to their reports, by the end of August 1937. no one planes were in stage of final assembly as well proposal state first to be delivered in May. Command of the Yugoslav Aviation did not want to ask for penalty as well that could make administrative troubles. Yugoslav officials also refuse German offer to equip planes with armament and aiming devices. In the meantime a group of Yugoslav workers and technicians came into Dornier for manufacture training.

 

          Maiden flight of the leading plane was at 6. October 1937 and first sample were deliver at October 25. 1937. The rest of the planes were delivering in the first months of 1938. During the delivery one plane, No.17 was lost and it was later replaced with the other one. At March 12. 1938 was signed new contract of delivery 14 new planes of the type and two of new model. Total Yugoslavia pay 7.139.995 RM for delivery of 36 Do17K from Germany. Also was made contract for license production of the plane in Yugoslavia and more 1.829.825 RM was pay for spare parts and materials.  From the report dated on February 6. 1939 could be noted that only ten planes from second contract was ferry to Yugoslavia and rest was in final stage of assembly or flight tests.

 

In total 36 planes was imported from Germany, from autumn 1937 to the beginning of 1939, in three versions. All of them was accepted and armed in VTZ Kraljevo and then preceded to the operational unit. Sole operator of the type was 3. vazduhoplovni puk [air regiment] with HQ base in Skoplje, South Serbia. The same unit had two groups. Crew was highly trained even for night operation. There were planes for unit to fly on shown widely in Europe but beginning of WW 2 stopped that idea. During the peacetime operations several accidents happen with completely lost of two planes. In the meantime revision was made on the German produced samples and in many times armament was changed.

 

          DFA factory in Kraljevo start with production of Do17K in May 15. 1939 and by the end of March 1940 fourteen planes was finished. First ten samples had the original French engines while the rest had domestic license built powerplants. In general three subtypes were built in DFA and till the April 1941 30 samples were built and deliver to the Yugoslav aviation. More three was delivering during the war and three was later rebuilt and deliver to the Croatia.

 

 

 

 

 

 

 

 

 

 

development     deployment      datafile      colors   combat   contact